Before installation, please check if the code no., size, tone and quality are the same in all the boxes and if they correspond to what indicates on the invoice. It is recommended to assemble a panel to evaluate the product before installation.


Installation Instructions

1. Base treatment- remove dusts on the ground, make sure the base must be clean, with no dirt or particles that affect the bonding strength of adhesive; Use hard object to strike the base, find out the hollow drum, and remove the arched cement agglomerate on the hollow drum; sweep the water to the base to make the base wet evenly, water infiltrate into the ground, but insure concrete and mortar base are not out of water, the water content is no more than 5%.



2. Blend the adhesive-Mix the latex and powder in a ratio of 1:4; How: Pour the latex first, then pour the powder, and stir with a blender to reach a uniform mixing state. (the mixed adhesive must be used up within one hour, it is forbidden to use after 1 hour or when the surface is agglomerated)



3. Coat the adhesive on base-After mixing the adhesive, it will take 3-5 minutes to cure the materials. The cured adhesive will be blended once again with a blender, so that the adhesive is fully mixed; Scrape a layer of adhesive on the ground, covering the surface, and then use a large amount of adhesive to scrape out 8mm thickness (the thickness depends on the actual situation).



4. Coat the adhesive to the back of tiles-Scrape a layer of adhesive on the back of the tile. Then use a large amount of adhesive to scrape out 8 mm thickness  (the thickness depends on the actual situation), supplement the adhesive on four sides of the tile and chamfer.


5. depends on the actual situation), supplement the adhesive on four sides of the tile and chamfer.



6. Paving- Cross paving is best, parallel paving is also feasible( as per adhesive's sloting direction)


7. Leave the gap and clean- Leave 1.0-1.5mm gaps between each tile as the width of the expansion joint is 1.0-1.5mm. And then clean the gap edges with sponges in time after paving. Leave 10mm structural expansion joints every 8-10 meters and should be deep to the base to prevent the stone from bulging or cracking due to the stress of the ground surface or structure.


图片24.png


8. Inspection

 

9. finished installation’s protection-After inspection of stone's installation is completed, a simple isolation belt should be set up to prevent personnel from walking around on this area.